Die 22 Projekte der PCI-Liste, die
Deutschland betreffen
|
Project of Common Interest/Cluster
of PCIs |
Description of PCI/s relevant for
the country concerned |
Priority corridor |
1.3. Cluster Denmark - Germany between
Endrup and Brunsbüttel including the following PCIs:
1.3.1. Interconnection between Endrup (DK) and Niebüll (DE)
1.3.2. Internal line between Brunsbüttel and Niebüll (DE)
|
New 380 kV AC lines (OHL) of about 200
km and with 3000 MVA capacity in Germany and about 80 km in Denmark
(onshore) and new transformers for integration of onshore wind in Schleswig-
Holstein, including lines: Brunsbüttel – Barlt (Süderdonn) –
Heide – Husum - Niebüllborder of Denmark Endrup. |
Electricity Northern Seas Offshore Grid
(NSOG) |
1.4. Cluster Denmark - Germany between
Kassø and Dollern including the following PCIs:
1.4.1. Interconnection between Kassø (DK) and Audorf (DE)
1.4.2. Internal line between Audorf and Hamburg/Nord (DE)
1.4.3. Internal line between Hamburg/Nord and Dollern (DE)
|
1.4.1.: Upgrade of existing 400kV
AC line and building a new 400kV route in Denmark with a total length
of 40 km.
1.4.2.: New 400kV AC double circuit line (OHL) mainly in the trace
of an existing 220kV line between Audorf and Hamburg/Nord, including
2 new 400/230kV transformers in substation Audorf.
1.4.3.:New 400kV AC double circuit line (OHL) between Dollern and
Hamburg/Nord, including 1 new 400/230kV transformer in substation
Hamburg/Nord and new 400kV switchgear in Kummerfeld. The total length
of German lines amounts to 195 km and a 4100 MVA capacity (onshore). |
Electricity Northern Seas Offshore Grid
(NSOG) |
1.8. PCI Germany - Norway interconnection
between Wilster (DE) and Tonstad (NO) [currently known as the NORD.LINK
project] |
A new HVDC subsea cable of minimum 500
kV, approximately 520-600 km and with a capacity of 1400 MW between
Southern Norway and Northern Germany (onshore and offshore). |
Electricity Northern Seas Offshore
Grid (NSOG) |
2.2. Cluster Belgium - Germany between
Lixhe and Oberzier [currently known as the ALEGrO project] including
the following PCIs:
2.2.1 Interconnection between Lixhe (BE) and Oberzier (DE)
2.2.2 Internal line between Lixhe and Herderen (BE)
2.2.3 New substation in Zutendaal (BE)
|
2.2.1.: Connection between Lixhe (BE)
and Oberzier (DE) including a new 100 km HVDC underground cable (voltage
under investigation) and the extension of existing 380 kV substations. |
Electricity WEST |
2.9. PCI Germany internal line between
Osterath and Philippsburg (DE) to increase capacity at Western borders |
New +/- 400 HVDC lines (OHL) with a length
of 40 km and 300 km of existing routes with new technology and with
a total capacity of 2000 MW from Osterath to Philippsburg to integrate
new wind generation especially from North/Baltic Sea towards Central-South
for consumption and storage (onshore). |
Electricity WEST |
2.10. PCI Germany internal line between
Brunsbüttel-Großgartach and Wilster-Grafenrheinfeld (DE)
to increase capacity at Northern and Southern borders |
New DC lines (OHL) with a total capacity
of 3.9 GW, with every line having a length between 670 and 770 km (voltage
tbd), to integrate new wind generation from northern Germany towards
southern Germany and southern Europe for consumption and storage (onshore). |
Electricity WEST |
2.11. Cluster Germany – Austria
- Switzerland capacity increase in Lake Constance area including the
following PCIs:
2.11.1. Interconnection between border area (DE), Meiningen (AT)
and Rüthi (CH)
2.11.2. Internal line in the region of point Rommelsbach to Herbertingen,
Herbertingen to Tiengen, point Wullenstetten to point Niederwangen
(DE) and the border area DE-AT
|
Construction of new 400 kV AC lines (OHL)
and extension of existing ones on approximately 380 km and with a total
capacity of 3500 MVA (tbd), and erection of a 400/220/110kV-substation.
Transmission routes include: Herbertingen - Tiengen, Herbertingen -
Pkt. Rommelsbach, Herbertingen - Meiningen (AT) – Rüthi (CH),
Pkt. Wullenstetten - Pkt. Niederwangen (onshore). |
Electricity WEST |
2.12. PCI Germany – Netherlands
interconnection between Niederrhein (DE) and Doetinchem (NL) |
New 380 kV AC double circuit (OHL) of
approximately 60 km and with a capacity of 2x2360 MVA between Niederrhein
and Doetinchem (onshore). |
Electricity WEST |
2.21. PCI hydro-pumped storage in Germany
- Riedl |
A pumped storage power plant with 300
MW installed capacity and an annual capacity of 330-462 GWh is planned
upstream from Jochenstein HPP at the Danube. Drawdown and return of
water will be ensured via Danube and a storage lake to be created southwest
of Gottsdorf town, approx. 350 m above the live storage of Jochenstein.
The upstream water conduit is designed as an inclined shaft. The downstream
water conduit joins the intake/outlet structure on the Danube underground. |
Electricity WEST |
3.1. Cluster
Austria - Germany between St. Peter and Isar including the following
PCIs:
3.1.1 Interconnection between St. Peter (AT) and Isar (DE)
3.1.2 Internal line between St. Peter and Tauern (AT)
3.1.3 Internal line between St. Peter and Ernsthofen (AT)
|
3.1.1.: 380 kV AC OHL between Isar and
St. Peter with a total capacity of 4.100 MVA, including 110 km of new
line in DE (including Pirach), 61 km of new circuit on an existing line,
new 380 kV switchgears in Altheim, Simbach, Pirach and St. Peter and
one new 380/220 kV transformer in the substations Altheim and St. Peter
and fourth circuit on the line between Isar and Ottenhofen (onshore). |
Electricity EAST |
3.12. PCI internal line in Germany between
Lauchstädt and Meitingen to increase capacity at Eastern borders |
New HVDC line (voltage tbd) with a length
of 450 km and a capacity of minimum 2000 MW to integrate especially
new wind generation from Baltic Sea towards Central/South Europe for
consumption and system stability improvement. The line type is planned
as OHL (onshore). |
Electricity EAST |
3.13. PCI internal line in Germany between
Halle/Saale and Schweinfurt to increase capacity in the North-South
Corridor East |
New 380 kV AC OHL of 110 km and with
a capacity of more than 3500 MVA between the substations Halle/Saale
and Schweinfurt (onshore). |
Electricity EAST |
3.14. Cluster Germany – Poland
between Eisenhüttenstadt and Plewiska [currently known as the GerPol
Power Bridge project] including the following PCIs:
3.14.1. Interconnection between Eisenhüttenstadt (DE) and Plewiska
(PL)
3.14.2 Internal line between Krajnik and Baczyna (PL)
3.14.3 Internal line between Mikulowa and Swiebodzice (PL)
|
3.14.1.: New AC 380 kV double circuit
OHL of 252 km and with a capacity of approximately 3750 MVA between
Eisenhüttenstadt and Plewiska (onshore) including the construction of
new substations Plewiska Bis (PL) and Gubin (PL). In the final stage
after 2022, also substation Zielona Góra between Gubin and Plewiska
Bis is planned to connect with this line. |
Electricity EAST |
3.15. Cluster Germany – Poland
between Vierraden and Krajnik including the following PCIs:
3.15.1 Interconnection between Vierraden (DE) and Krajnik (PL)
3.15.2 Coordinated installation and operation of phase shifting transformers
on the interconnection lines between Krajnik (PL) – Vierraden
(DE) and Mikulowa (PL) – Hagenwerder (DE) |
3.15.1.: Upgrade of existing 220
kV AC OHL between Vierraden and Krajnik to 380 kV double circuit OHL
with a length of 26 km and a capacity of approximately 3500 MVA (onshore).
The upgrade of the line is on condition that the line is equipped
with a PST (PCI 3.15.2.) in order to ensure the system security and
stability in case of high flows on the mentioned line. The PST has
to be installed and operated by cooperation of Germany and Poland.
3.15.2.: Installation of Phase Shifting Transformers (PSTs) on the
upgraded interconnection between Krajnik (PL) and Vierraden (DE) and
phase shifting transformers (PSTs) on the existing interconnection
between Mikulowa (PL) and Hagenwerder (DE). |
Electricity EAST |
4.1. PCI Denmark – Germany interconnection
between Ishoj/Bjæverskov (DK) and Bentwisch/Güstrow (DE) via offshore
windparks Kriegers Flak (DK) and Baltic 2 (DE) [currently known as Kriegers
Flak Combined Grid Solution] |
The Kriegers Flak Combined Grid Solution
is the new offshore multi-terminal connection between Denmark and Germany
used for both grid connection of offshore wind farms Kriegers Flak and
interconnection. Exact technical features still have to be determined,
but the project envisages 270 km of mainly offshore and partially onshore
HVDC cables with a voltage of ±320 kV and a capacity around 600 MW. |
Electricity Baltic Energy Market Interconnectio
n Plan (BEMIP) |
5.10. PCI Reverse flow interconnection
on TENP pipeline in Germany |
Reverse flow at the pipeline section
between the interconnection point at Walbach and Bocholtz, with a daily
capacity of 22 GWh and with a possible later expansion to 60 GWh (onshore).The
power of the compressor station is 8 MW. |
Gas WEST |
5.12. PCI Reverse flow interconnection
on TENP pipeline to Eynatten interconnection point (Germany) |
Reverse flow interconnection at Eynatten
on TENP pipeline (on a distance of 11 km), determining an additional
daily capacity of 5.5 to 22.8 MCM/day from DE to BE and that of 5.5
to 41 MCM/day from BE to DE (onshore). The power of the compressor station(s)
will be between 12 and 36 MW, depending on the chosen alternative. |
Gas WEST |
5.18. PCI Reinforcement of the German
network to reinforce interconnection capacities with Austria [currently
known as Monaco pipeline phase I (Haiming/Burghausen-Finsing)] |
New pipeline of 90 km with a daily capacity
of 52.8 MCM/day, including two steering and metering stations. Off-take
points are located in Haiming, and Finsing have as annual volumes values
3.7 and 2.8 BCM/year respectively. |
Gas WEST |
6.16. PCI Tauerngasleitung (TGL) pipeline
between Haiming (AT)/Überackern (DE) – Tarvisio (IT) |
New onshore pipeline with a total length
of approximately 290 km crossing the Alps via 10 tunnels with an approximate
length of 25 km. The daily capacity in both flow directions will be
of maximum 31.2 MCM/day. The power of the compressor station(s) in Auerbach
and Feistritz will be of approximately 2 x 33 MW. |
Gas EAST |
8.4. PCI Capacity expansion on DK-DE
border |
Extension of onshore pipeline with a
length of approximately 63.5 km. The power of the compressor station
is (2+1) x 7.69 MW. |
Gas Baltic Energy Market Interconnectio
n Plan (BEMIP) |
9.4. PCI Litvinov (Czech Republic)-Spergau
(Germany) pipeline: the extension project of the Druzhba crude oil pipeline
to the refinery TRM Spergau |
A pipeline between Litvinov (CZ) and
Spergau (DE) with a diameter of 700 mm and a length of 160 km. |
Oil Supply Connections in Central Eastern
Europe (OSC) |
9.6. PCI TAL Plus: capacity expansion
of the TAL Pipeline between Trieste (Italy) and Ingolstadt (Germany) |
Increasing capacity of the TAL pipeline
in its first section between Trieste and Ingolstadt to allow for full
diversification of oil supply to the Czech Republic. |
Oil Supply Connections in Central Eastern
Europe (OSC) |