Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL on the internal market for electricity (23. 2. 2017)

(Vollständiger Text als PDF)


Article 11

Dispatching of generation and demand response

1. Dispatching of power generation facilities and demand response shall be non-discriminatory and market based unless otherwise provided under paragraphs 2 to 4.

2. When dispatching electricity generating in stallations, transmission system operators shall give priority to generating installations using renewable energy sources or high- efficiency cogeneration from small generating installations or generating installations using emerging technologies to the following extent:

(a) generating installations using renewable energy sources or high-efficiency cogeneration with an installed electricity capacity of less than 500 kW; or

(b) demonstration projects for innovative technologies.

3. Where the total capacity of generating installations subject to priority dispatch under paragraph 2 is higher than 15 % of the total installed generating capacity in a Member State, point (a) of paragraph 2 shall apply only to additional generating installations using renewable energy sources or high-efficiency cogeneration with an installed electricity capacity of less than 250 kW.

From 1 January 2026, point (a) of paragraph 2 shall apply only to generating installations using renewable energy sources or high-efficiency cogeneration with an installed electricity capacity of less than 250 kW or, if the threshold under the first sentence of this paragraph has been reached, of less than 125 kW.

4. Generating installations using renewable energy sources or high-efficiency cogeneration which have been commissioned prior to [OP: entry into force] and have, when commissioned, been subject to priority dispatch under Article 15(5) of Directive 2012/27/EU of the European Parliament and of the Council or Article EN 45 EN 16(2) of Directive 2009/28/ EC of the European Parliament and of the Council 39 shall remain subject to priority dispatch. Priority dispatch shall no longer be applicable from the date where the generating installation is subject to significant modifications, which shall be the case at least where a ne w connection agreement is required or the generation capacity is increased.

5. Priority dispatch shall not endanger the secure operation of the electricity system, shall not be used as a justification for curtailment of cross-border capacities beyond what is provided for in Article 14 and shall be based on transparent and non-discriminatory criteria.